Description
The works consisted of burying the M-30 highway, in a section of more than 600 m in length and 40 m in width as it passes through the old Vicente Calderón stadium, and in expanding the area of Madrid Río, to an urban park that will run along the bed of the Manzanares River
Project Data
- Client: JV FERROVIAL S.A. and ACCIONA S.A.
- Owner: Ayuntamiento de Madrid
- Completion date: 2023
- Products provided: T beams, placas armadas de ancho variable y prelosas pretensadas
- Precast Volume: 8.375 m3
Scope of Works
Design, manufacturing, transportation and assembly of 11.439 precast slabs, place on 481 T beams with a total volume of concrete of 8,375 m3.